Brand:aa
Product detail:
PP PE Plastic Granules Making Machine
This production line is ideal equipment for recycled plastic pe material. pe material can be from pe pipe, pe milk bottle, pe film etc
The machine line layout is as following.
SJ-65 parallel twin screw extruding motor machine:
The motor machine adopts parallel twin screw extruding design. it cantains electromotor, metering feeder, twin screw extruder, oil cooling tank and others.
Type: SJ-65
Screw Material: W6Mo5Cr4V2
Main motor power:55kw
Total heating power:1.75kw*2*8+1.5kw*2*2
Screw diameter:62.5mm
Screw length:2400mm
Ratio of screw:40:1
Gearbox :Imitated Germany professional gearbox
Metering feeder power: 3kw
Metering Feeder: double screw feeder with rated volume
Hydraulic Screen Exchanger System :
Double position hydraulic screen changer for No stopping ,no leaking
Screen changing time≤2 sec.
Motor power:2.2kW
Water Ring, Face Cutting System
Water-ring granulation motor power 1.5kW.Water Pump:4Kw
Speed controlling by frequency conversion.
Include:hot cutting die, diffluence strick, water-ring cover, knife, cutterhead,toolbar,ect.
Centerifugal dewatering:
Material:bracket jointing by Q235,the others are stainless steel
Motor power:4Kw
Rotate speed:1500rpm
Vibration Screen:
Power:0.22kw*2
Size:2500*600*1200mm
Weight: 350kg
Air conveyer:
Power: 4kw
Pipe line and tee join T are made by stainless steel
Electrical control system:
Japanese“RKC”Temperature controlling system
Germany “ABB” converter control for belt conveyer, compact and extruder
Contactor, Relay: SIMENS
Other low pressure electric is SCHNEIDER
Supply the wire cable which connect the main machine and cabinet
OUR SERVICE
1. We can send the engineers to help installing, commissioning and training, 60$ one people per day after the engineers start from our factory area.
The visa fee will be in buyer's account;
The air ticket, hotel accommodation etc will be in the buyer's account;
The buyer should prepare the factory plant, water supply, air supply, power supply before our engineer arrived;
The buyer should send enough worker to cooperate working with our engineer and supply the necessary tools for working;
2. We supply below necessary documents with the machine:
Machine layout
Electricity diagram
Machine certificate
General manual book/maintenance book
3. We provides one-year quality guarantee. During this period, if the machine’s malfunction is approved to be our responsibility, we will send the broken spare parts to you with DHL courier within 7 workdays after receiving the complainant. After one year guarantee, the seller provides payable spare parts and technician’s VISITING maintenance service. You should buy the technician’s air tickets, hotel accommodation etc and US$50/day after landed in the factory area.
The supplier shall not incur any liability for the purchaser in the event that it is delayed in the performance of its obligations by force major. Force major shall mean any cause of delay beyond the reasonable control of the seller, including but not limited to strikes, lockouts, riots, sabotage, failure or delay on the part of any other supplier or suppliers, act of war or destruction of essential equipment by fire, explosion, storm, flood or delay caused by failure of power supplies or transport facilities.